Project Controls at design stage, is it Essential to Project Success?

This course on project controls is brought to you by GBRI's partnership with Project Controls Expo. Click here to learn more
PCE-Virtual-logo
Varughese Mathew
· Published on:July 24, 2021

Project No: 1
A mega project, after many years of extensive unique design, tender return was 50% higher than the approved budget. Tried various value engineering exercise to reduce cost, several years passed project still not awarded.

Project No. 2
Another mega project, Project commenced, contract awarded without full design. Extensive changes during design development. Massive claim poured in from Contractors. Project stopped. Feasibility and rate of return in question. Not sure the outcome of the project.

Both project identity will be kept confidential.

Varughese Mathew

Managing Director for Elixir Project Consultants DWC LLC

    About Instructor

    Shafeeq

    41 Courses

    Not Enrolled

    Course Includes

    • 1 Lesson

    Responses

    Your email address will not be published.

    The journey to become a sustainability guru begins here!
    Jeslin Varghese
    gbri-logo

    Sustainability education should not have any boundaries!

    Register now to get started.

    OR REGISTER WITH
    GBRI is your #1 source for sustainability education with more than 250 courses to choose from!
    gbri-logo

    Welcome back!

    Login to access your sustainability courses, certificates, badges, community and more!
    OR LOGIN WITH