EQ Credit: Construction Indoor Air Quality (IAQ) Management Plan
👉 “Clean during construction = healthy after occupancy”
This credit is about protecting air quality during construction so that:
Workers are protected during construction Occupants are protected after occupancy Building systems perform better long-term 👉 Think: “Don’t contaminate the building before people even move in.”
🎯 Intent
To promote the well-being of construction workers and building occupants by minimizing indoor air quality problems associated with construction and renovation.
✅ Core Requirement
Projects must:
✔ Develop AND implement a Construction IAQ Management Plan ✔ Follow SMACNA IAQ Guidelines (key exam item)
📊 REQUIRED STRATEGIES (SMACNA + LEED)
🔹 Must Address ALL of These
Requirement
What It Means
Exam Tip
Follow SMACNA Guidelines
Control dust, pollutants, airflow
⭐ Core requirement
Protect absorptive materials
Prevent moisture damage (e.g., drywall, insulation)
Mold prevention
HVAC protection
Use MERV 8 filters if running systems
⭐ Compare with MERV 13
No tobacco use
No smoking inside or within 25 ft
Same as ETS prereq
🧠 SMACNA STRATEGIES (MEMORIZE THIS LIST)
Category
Meaning
HVAC Protection
Keep ducts/equipment clean
Source Control
Control dust at source
Pathway Interruption
Prevent pollutant spread
Housekeeping
Clean regularly
Scheduling
Sequence work to reduce exposure
👉 Memory Trick: “HSPHS” → HVAC, Source, Pathway, Housekeeping, Scheduling
⚠️ KEY NUMBERS TO REMEMBER
Item
Value
Smoking distance
25 feet
Filter requirement
MERV 8 (during construction)
Enhanced IAQ (comparison)
MERV 13 (post-construction)
🏗️ IMPLEMENTATION (PROJECT TIP)
Include IAQ plan in:Construction documents Specifications Subcontractor agreements 👉 This is often tested:
“Where should the IAQ plan be included?” → Construction documents (Specifications)
🏥 HEALTHCARE ADD-ON (VERY TESTABLE)
Healthcare projects require:
🔹 Environmental Quality Management Plan (EQMP)
Requirement
Description
Infection Control Risk Assessment (ICRA)
Evaluate contamination risks
Follow FGI Guidelines (2010)
Healthcare standard
Integrative team
Owner + Designer + Contractor
Coordinate with design
Not just construction phase
👉 Exam Tip: Healthcare ≠ just IAQ → includes infection control
👉 During construction:
Keep air clean Protect materials Protect HVAC No smoking Follow SMACNA ❗ COMMON EXAM TRAPS
MERV 8 (this credit) vs 13 (Enhanced IAQ) Plan must be implemented , not just written Smoking restriction applies during construction SMACNA = construction phase , not operations
Official FAQs Which standard must be followed for this credit? A. ASHRAE 62.1
B. SMACNA IAQ Guidelines
C. CIBSE Manual
D. EPA WaterSense
✅ Answer: B
What is the minimum filtration requirement if HVAC is used during construction? A. MERV 13
B. MERV 10
C. MERV 8
D. MERV 5
✅ Answer: C
A contractor stores drywall in an open, humid area. Which requirement is being violated? A. Source control
B. HVAC protection
C. Protection of absorptive materials
D. Pathway interruption
✅ Answer: C
A project includes IAQ measures but does not include them in construction documents. What is the issue? A. No issue
B. Plan is incomplete
C. Plan is not enforceable
D. Violates ASHRAE
✅ Answer: C
A project runs HVAC systems during construction without filtration. What are the likely impacts? A. Improved airflow
B. Contaminant buildup in ducts
C. Energy savings
D. Better commissioning
✅ Answer: B
A healthcare project follows SMACNA but skips infection control risk assessment. Does it comply? A. Yes
B. No
C. Only for new construction
D. Only if HVAC is off
✅ Answer: B