Construction Waste Management in LEED v4
Official FAQs
Which of the following is a requirement of MR Prerequisite: Construction and Demolition Waste Management Planning?
A. Divert at least 50% of construction waste
B. Identify at least five material streams
C. Limit waste generation to 2.5 lbs/sf
D. Use only source separation
✅ Answer: B
Explanation:
The prerequisite requires identifying at least 5 material streams.
👉 It does NOT require any diversion percentage (common trap).
B. Identify at least five material streams
C. Limit waste generation to 2.5 lbs/sf
D. Use only source separation
✅ Answer: B
Explanation:
The prerequisite requires identifying at least 5 material streams.
👉 It does NOT require any diversion percentage (common trap).
Which of the following best describes the intent of MR Credit: Construction and Demolition Waste Management?
A. Develop a waste management plan
B. Reduce indoor air contamination
C. Divert construction waste from landfill and reduce total waste generated
D. Track building energy use
✅ Answer: C
Explanation:
The credit focuses on actual performance—diversion and/or reduction.
B. Reduce indoor air contamination
C. Divert construction waste from landfill and reduce total waste generated
D. Track building energy use
✅ Answer: C
Explanation:
The credit focuses on actual performance—diversion and/or reduction.
(Requested “All Except” Question) Construction and demolition debris includes all of the following EXCEPT:
A. Concrete
B. Wood
C. Hazardous waste
D. Drywall
✅ Answer: C
Explanation:
Hazardous waste is excluded from LEED C&D calculations.
👉 Only non-hazardous construction waste counts.
B. Wood
C. Hazardous waste
D. Drywall
✅ Answer: C
Explanation:
Hazardous waste is excluded from LEED C&D calculations.
👉 Only non-hazardous construction waste counts.
A project creates a plan identifying five material streams but does not track diversion percentages. Which requirement has the project met?
A. MR Credit: Construction and Demolition Waste Management
B. MR Prerequisite: Construction and Demolition Waste Management Planning
C. MR Credit: Building Product Disclosure and Optimization
D. MR Prerequisite: Storage and Collection of Recyclables
✅ Answer: B
Explanation:
The prerequisite is about planning, not performance.
👉 No diversion tracking required to meet the prerequisite.
B. MR Prerequisite: Construction and Demolition Waste Management Planning
C. MR Credit: Building Product Disclosure and Optimization
D. MR Prerequisite: Storage and Collection of Recyclables
✅ Answer: B
Explanation:
The prerequisite is about planning, not performance.
👉 No diversion tracking required to meet the prerequisite.
A project diverts 60% of construction waste across 3 material streams. Which credit level has the project achieved under MR Credit: Construction and Demolition Waste Management?
A. No credit
B. 1 point
C. 2 points
D. Exemplary performance
✅ Answer: B
Explanation:
• ≥50% diversion + ≥3 streams → 1 point (Path 1)
• ≥75% + ≥4 streams → 2 points
B. 1 point
C. 2 points
D. Exemplary performance
✅ Answer: B
Explanation:
• ≥50% diversion + ≥3 streams → 1 point (Path 1)
• ≥75% + ≥4 streams → 2 points
A project generates only 2.0 lbs/sf of construction waste. Which option under MR Credit: Construction and Demolition Waste Management does this support?
A. Option 1 – Diversion
B. Option 2 – Total Waste Reduction
C. Both options
D. Neither
✅ Answer: B
Explanation:
Option 2 focuses on source reduction, not diversion.
👉 Threshold = ≤ 2.5 lbs/sf
B. Option 2 – Total Waste Reduction
C. Both options
D. Neither
✅ Answer: B
Explanation:
Option 2 focuses on source reduction, not diversion.
👉 Threshold = ≤ 2.5 lbs/sf
A project uses a commingled waste system and sends all waste to a facility that provides verified diversion reports. How are material streams counted for MR Credit: Construction and Demolition Waste Management?
A. Counts as one material stream only
B. Cannot be counted
C. Can count as multiple streams if properly documented
D. Automatically qualifies for 2 points
✅ Answer: C
Explanation:
👉 Commingled waste can count as multiple streams
ONLY if facility provides documentation
B. Cannot be counted
C. Can count as multiple streams if properly documented
D. Automatically qualifies for 2 points
✅ Answer: C
Explanation:
👉 Commingled waste can count as multiple streams
ONLY if facility provides documentation
Which of the following waste management strategies would NOT contribute toward diversion under MR Credit: Construction and Demolition Waste Management?
A. Recycling concrete
B. Donating wood
C. Using waste as alternative daily cover (ADC)
D. Salvaging metal
✅ Answer: C
Explanation:
👉 ADC = does NOT count as diversion (major exam trap)
B. Donating wood
C. Using waste as alternative daily cover (ADC)
D. Salvaging metal
✅ Answer: C
Explanation:
👉 ADC = does NOT count as diversion (major exam trap)
A project team focuses on prefabrication and modular construction to reduce material waste. Which strategy under MR Credit: Construction and Demolition Waste Management does this represent?
A. Diversion
B. Recycling
C. Source reduction
D. Waste-to-energy
✅ Answer: C
Explanation:
👉 Source reduction = highest priority in waste hierarchy
B. Recycling
C. Source reduction
D. Waste-to-energy
✅ Answer: C
Explanation:
👉 Source reduction = highest priority in waste hierarchy
A project sends construction waste to a waste-to-energy facility instead of recycling, even though recycling facilities are available nearby. How would this impact compliance?
A. Fully acceptable and preferred
B. Counts as diversion automatically
C. Not preferred and may not count toward LEED credit
D. Required under LEED
✅ Answer: C
Explanation:
👉 Waste-to-energy:
• Not preferred
• Only allowed under strict conditions
• Recycling is always prioritized
B. Counts as diversion automatically
C. Not preferred and may not count toward LEED credit
D. Required under LEED
✅ Answer: C
Explanation:
👉 Waste-to-energy:
• Not preferred
• Only allowed under strict conditions
• Recycling is always prioritized
Which statement best distinguishes the prerequisite from the credit?
A. Both require 50% diversion
B. Prerequisite requires performance; credit requires planning
C. Prerequisite requires planning; credit requires measurable performance
D. Both are optional
✅ Answer: C
B. Prerequisite requires performance; credit requires planning
C. Prerequisite requires planning; credit requires measurable performance
D. Both are optional
✅ Answer: C
How is diversion rate calculated under MR Credit: Construction and Demolition Waste Management?
A. Diverted waste ÷ recycled waste
B. Diverted waste ÷ total waste generated
C. Total waste ÷ landfill waste
D. Recycled waste ÷ total materials used
✅ Answer: B
B. Diverted waste ÷ total waste generated
C. Total waste ÷ landfill waste
D. Recycled waste ÷ total materials used
✅ Answer: B