0
0
Subtotal: $0.00

No products in the cart.

Return To Shop

EQ Credit: Indoor Air Quality Assessment (1โ€“2 Points)

๐Ÿ‘‰ โ€œFlush it OR prove itโ€”but donโ€™t mix it.โ€

This credit ensures that:

๐Ÿ‘‰ After construction, the air is actually clean before people use the building

You can either:

  • Flush the building with fresh air
    OR
  • Test the air to prove it’s clean

๐ŸŽฏ Intent

To establish better indoor air quality after construction and during occupancy.

๐Ÿ”„ TWO OPTIONS (CORE STRUCTURE)

Option

Approach

Best For

Option 1: Flush-Out

Flush building with outdoor air

Simpler, no testing

Option 2: Air Testing

Test contaminants in air

Faster occupancy

๐ŸŒฌ๏ธ OPTION 1: FLUSH-OUT (MOST TESTED)

๐Ÿ”น Two Paths

Path

When Used

Requirement

Before Occupancy

Building empty

14,000 cu ft/sf of outdoor air

During Occupancy

Occupancy starts early

Start at 3,500 cu ft/sf, then continue

ย 

๐Ÿ“Š KEY REQUIREMENTS (MEMORIZE THESE)

Parameter

Value

Total air required

14,000 cu ft/sf

Partial flush (before occupancy)

3,500 cu ft/sf

Ventilation rate (during occupancy)

0.30 cfm/sf

Temperature

60โ€“80ยฐF

Humidity

โ‰ค 60%

โš ๏ธ DURING OCCUPANCY RULES

If using Path 2:

  • Must continue flushing until 14,000 cu ft/sf total
  • Ventilation must:
    • Start 3 hours before occupancy
    • Continue during occupancy

๐Ÿง  MEMORY TRICK

๐Ÿ‘‰ โ€œ3,500 โ†’ 14,000 โ†’ 0.30โ€

  • Start = 3,500
  • Finish = 14,000
  • Rate = 0.30

๐Ÿงช OPTION 2: AIR TESTING

๐Ÿ”น When to Use

  • Faster occupancy needed (Possible Exam Question)
  • Want proof instead of flushing

ย 

๐Ÿ“Š REQUIREMENTS

Requirement

Details

Timing

After construction, before occupancy

Conditions

Normal occupied ventilation

Sampling

Breathing zone

Locations

โ‰ฅ 1 per space + โ‰ฅ 1 per floor

Retesting

Required if limits exceeded

โš ๏ธ SPECIAL NOTE

  • Retail projects: testing allowed within 14 days after occupancy

๐Ÿšซ CRITICAL RULE

๐Ÿ‘‰ Options CANNOT be combined

๐Ÿงฑ COMMON REQUIREMENT (BOTH OPTIONS)

Before either option:

โœ” All finishes must be installed
โœ” VOC sources must be complete

Examples:

  • Paint
  • Carpet
  • Furniture
  • Ceiling tiles

๐Ÿ‘‰ Possible Question Alert

โš ๏ธ COMMON EXAM TRAPS

Trap

Reality

Flush-out is optional

Must choose one option

Air testing can be partial

Must meet all thresholds

HVAC not needed

Must run at normal conditions

Can combine options

โŒ Not allowed

Flush-out before finishes

โŒ Must be after finishes

๐Ÿ‘‰ Two choices:

  • Flush the air
  • Test the air

๐Ÿ‘‰ But always:

  • Finish construction first
  • Prove clean air before occupancy

Official FAQs

What is the total outdoor air required for a full flush-out?
A. 3,500 cu ft/sf
B. 10,000 cu ft/sf
C. 14,000 cu ft/sf
D. 0.30 cfm/sf
โœ… Answer: C
What is the minimum ventilation rate during occupancy flush-out?
A. 0.10 cfm/sf
B. 0.30 cfm/sf
C. 1.0 cfm/sf
D. 14,000 cfm
โœ… Answer: B
A project begins occupancy after delivering 3,500 cu ft/sf but stops ventilation. What is wrong?
A. Nothing
B. Needs higher temperature
C. Must continue ventilation until 14,000 cu ft/sf
D. Must switch to testing
โœ… Answer: C
A project performs IAQ testing before installing carpets and furniture. Is this compliant?
A. Yes
B. No
C. Only for retail
D. Only if HVAC is off
โœ… Answer: B
A project wants early occupancy but minimal disruption. Which option is best?
A. Flush-out before occupancy
B. Flush-out during occupancy
C. Air testing
D. Skip IAQ credit
โœ… Answer: C
Air testing shows high VOC levels in one zone. What must the team do?
A. Ignore it
B. Reduce ventilation
C. Retest entire building
D. Correct issue and retest affected area
โœ… Answer: D

Comments

No comments yet. Be the first to post!

Leave a Reply

Scroll to Top
GBRI is your #1 source for sustainability education with more than 400+ courses to choose from!
gbri-logo

Welcome back!

Login to access your sustainability courses, certificates, badges, community and more!
Celebrate this New Year 2026 With 40% OFF LEED ,WELL, CE & membership Programs!
LEED, WELL, CE & Membership Programs

40% Off

Achieve your sustainability goals for less. Grab your discount before you go.

GBRI

Memorial Day Sale

June 1 to June 15 - 2024

GBRI

Annual Day Sale

March 15 to April 21 - 2024

The journey to become a sustainability guru begins here!
Jeslin Varghese
gbri-logo

Sustainability education should not have any boundaries!

Register now to get started.

OR REGISTER WITH