EQ PREREQ – Environmental Tobacco Smoke (ETS) Control
Official FAQs
What is the minimum required distance for outdoor smoking areas from building entrances?
A. 10 feet
B. 15 feet
C. 25 feet
D. 50 feet
✅ Answer: C
B. 15 feet
C. 25 feet
D. 50 feet
✅ Answer: C
Where must no-smoking signage be located?
A. At property boundary
B. Within 25 feet of entrances
C. Within 10 feet of entrances
D. Inside only
✅ Answer: C
B. Within 25 feet of entrances
C. Within 10 feet of entrances
D. Inside only
✅ Answer: C
Which of the following is allowed under LEED?
A. Indoor smoking rooms with ventilation
B. Smoking in mechanical rooms
C. Smoking in designated outdoor areas ≥25 ft away
D. Smoking near air intakes
✅ Answer: C
B. Smoking in mechanical rooms
C. Smoking in designated outdoor areas ≥25 ft away
D. Smoking near air intakes
✅ Answer: C
A building allows smoking 15 feet from the entrance. Does it comply?
A. Yes
B. No
✅ Answer: B
Explanation:
Minimum distance is 25 feet
B. No
✅ Answer: B
Explanation:
Minimum distance is 25 feet
A cafe places seating on a public sidewalk outside its property line. What must the project do?
A. No requirement
B. Allow smoking
C. Prohibit smoking in that area
D. Install filtration systems
✅ Answer: C
Explanation:
If used for business → must control smoking
B. Allow smoking
C. Prohibit smoking in that area
D. Install filtration systems
✅ Answer: C
Explanation:
If used for business → must control smoking
A residential building prohibits smoking in common areas and includes it in lease agreements. Which option is this?
A. Option 1
B. Option 2
C. Both
D. Not compliant
✅ Answer: B
B. Option 2
C. Both
D. Not compliant
✅ Answer: B
A project cannot meet the 25-foot rule due to local code restrictions. What should the team do?
A. Ignore LEED requirement
B. Cancel certification
C. Provide documentation of code limitation
D. Move entrances
✅ Answer: C
B. Cancel certification
C. Provide documentation of code limitation
D. Move entrances
✅ Answer: C
Which strategy BEST achieves the intent of this prerequisite Environmental Tobacco Smoke (ETS) Control?
A. Installing better filters
B. Increasing ventilation
C. Eliminating smoking exposure
D. Monitoring CO₂ levels
✅ Answer: C
B. Increasing ventilation
C. Eliminating smoking exposure
D. Monitoring CO₂ levels
✅ Answer: C
Which project type has the MOST stringent ETS requirement?
A. Office building
B. Residential building
C. School
D. Retail
✅ Answer: C
Explanation:
Schools require no smoking on entire site
B. Residential building
C. School
D. Retail
✅ Answer: C
Explanation:
Schools require no smoking on entire site
Comments